Jessco, Inc. v. Builders Mutual Insurance Co: Part 1 - “Your Work,” Late Notice, and the Duty to Indemnify

Post by Logan Wells
A recent opinion of the United State Court of Appeals for the Fourth Circuit addressed a multitude of issues presented in litigation involving commercial general liability policies – the “your work” exclusion, late notice, and the duty to indemnify.

On March 29, 2012, in Jessco, Inc. v. Builders Mutual Insurance Co., the Fourth Circuit affirmed in part, reversed in part, and remanded by unpublished per curiam opinion the judgment of the United States District Court for the District of South Carolina, thereby finding that Builders Mutual Insurance Co. (“BMIC”) had a duty to defend Jessco, Inc. (“Jessco”) in the underlying construction-defect action, but BMIC was not obligated to indemnify Jessco for the re-grading allowance it paid to the underlying plaintiff homeowners.

In Jessco, Inc., the Mazycks hired Jessco to build a house in a North Charleston subdivision. After moving into the house in 2004, they provided Jessco with a punch list of items to be completed or repaired. These items were not resolved to the Mazycks’ liking, and in 2005, they filed the underlying suit against Jessco, alleging, among other things, that their lot flooded due to improper grading. In 2006, the action was stayed so the claims could be arbitrated. In the fall of 2007, experts for the Mazycks identified water damage to the house caused by the flooding of the property.

In October 2007, after the escalation in the Mazycks' demands, Jessco finally notified BMIC of the underlying claims. BMIC concluded the claims were not covered by the Policy and Jessco failed to promptly notify BMIC of the lawsuit. Accordingly, BMIC refused to defend or indemnify Jessco with regard to the underlying suit. Jessco thereafter filed a declaratory judgment action seeking a declaration that the claims in the underlying action were covered by the Policy. BMIC counterclaimed, seeking a declaration that it was not obligated to defend or indemnify Jessco.

The arbitration hearing on the Mazycks' claims was conducted in late 2008. The arbitrator issued his award in April 2009, ordering Jessco to pay almost $55,000 in damages. As to the flooding issue, the arbitrator concluded the flooding was proximately caused by "the overcapacitation of the wetlands, caused by the overall design and development of the surrounding neighborhood." Although the arbitrator found that Jessco's work was "not the legal proximate cause of the flooding of [the Mazycks'] property," the award included a $10,000 allowance for re-grading of the lot. BMIC appealed, challenging the district court’s determination that (1) BMIC had a duty to defend Jessco in the underlying action; and (2) BMIC had a duty to indemnify Jessco for the re-grading allowance.

Duty to Defend

In asserting it had no duty to defend, BMIC argued (1) coverage for the Mazycks’ claims was excluded by the Policy’s “your work” exclusion; and (2) Jessco failed to notify BMIC of the underlying lawsuit “as soon as practicable” as required by the Policy.

BMIC did not dispute on appeal that the allegations of the underlying complaint raised the possibility of “property damage” caused by an “occurrence,” but instead contended it had no duty to defend because coverage for the claims was excluded under the “your work” exclusion, which excluded coverage for any claims of “’[p]roperty damage’ to ‘your work’ arising out of it or any part of it.” “Your work” was defined as “[w]ork or operations performed by you or on your behalf,” a definition broad enough to encompass and preclude coverage for work done by the insured’s subcontractors. Although the Policy included an exception restoring coverage for damage to work performed by a subcontractor, it also contained an endorsement removing the subcontractor exception.

BMIC argued all the work on the property was done by subcontractors on Jessco’s behalf, and therefore, the “your work” exclusion barred coverage for all underlying claims. The court disagreed, noting “the exclusion does not withdraw coverage for any and all work done by the insured or its subcontractors; it withdraws coverage in cases where the insured causes property damage to work done by the insured or its subcontractors... ‘It does not exclude coverage for a third party’s work.’” (Emphasis in original) (quoting Limbach Co. v. Zurich Am. Ins. Co., 396 F.3d 358, 365 (4th Cir. 2005) (per curiam)). Thus, the court concluded, “the Policy’s elimination of the subcontractor’s exception means that Jessco’s subcontractors will not be viewed as third-parties for purposes of determining whose ‘work’ was damaged, but the elimination of the exception does not, as BMIC contends, preclude coverage if Jessco’s work in fact damages the work of a third party.”

The court determined the Mazycks’ claims against Jessco created a possibility that a third-party’s work or property was damaged by the faulty workmanship of Jessco or its subcontractors, noting the contract between Jessco and the Mazycks specifically contemplated that Mr. Mazyck would perform some of the work, and that Mr. Mazyck himself installed (or hired a subcontractor to install) the flooring and landscaping. Accordingly, the court found the “your work” exclusion did not bar coverage for the underlying claims.

With regard to “late notice,” BMIC argued even if the Policy otherwise provided coverage, Jessco lost its right to coverage by waiting more than two years to give notice of the underlying suit. Assuming for purposes of the opinion that notice was untimely, the court noted that under South Carolina law, “recovery under the Policy is barred only if BMIC proves that it was substantially prejudiced by the late notice.” See Vermont Mut. Ins. Co. v. Singleton, 446 S.E.2d 417, 421 (S.C. 1994) (“Where the rights of innocent parties are jeopardized by a failure of the insured to comply with the notice requirements of an insurance policy, the insurer must show substantial prejudice to the insurer’s rights.”); Squires v. National Grange Mut. Ins. Co., 145 S.E.2d 673, 677 (S.C. 1965) (“The burden of proof is upon the insurer to show not only that the insured has failed to perform the terms and conditions invoked upon him by the policy contract but in addition that it was substantially prejudiced thereby.”) Therefore, because BMIC failed to present any evidence of prejudice and “prejudice to the insurer may not be presumed,” the court rejected BMIC’s assertion that Jessco’s delay in notification precluded recovery under the Policy.

            BMIC also challenged the attorney fee award; however, it failed to substantively address the issue in its brief. Accordingly, the court found BMIC had abandoned the issue. See Wahi v. Charleston Area Med. Ctr., Inc., 562 F.3d 599, 607 (4th Cir. 2009) (“Federal Rule of Appellate Procedure 28(a)(9)(A) requires that the argument section of an appellant’s opening brief must contain the ‘appellant’s contentions and the reasons for them, with citations to the authorities and parts of the record on which the appellant relies.’ Because Wahi has failed to comply with the specific dictates of Rule 28(a)(9)(A), we conclude that he has waived his claims . . . .”).

Duty to Indemnify

BMIC also contended that the $10,000 re-grading allowance was not compensation for loss caused by a covered risk. Recognizing the Mazycks asserted contract and negligence based claims against Jessco in the underlying action, the Court determined that if the re-grading allowance was awarded by the arbitrator as compensation for negligence by Jessco in grading the property, Jessco’s negligence would constitute an “occurrence,” and the policy would provide coverage. Thus, the court first determined the legal basis for the re-grading allowance ordered by the arbitrator:

Although the arbitrator stated that Jessco and the Mazycks both “b[ore] some responsibility for the flooding,” the arbitrator ultimately determined that the flooding was caused by “the overcapacitation of the wetlands, caused by the overall design and development of the surrounding neighborhood.” The arbitrator concluded that the development and overcapacitation was “an unforeseen intervening cause,” and Jessco’s work was “not the legal proximate cause of the flooding of [the] property.”
The arbitrator’s determination that Jessco’s work was not the proximate cause of the flooding necessarily amounted to a rejection of any negligence-based claim asserted against Jessco. See, e.g., Hurd v. Williamsburg Cnty., 579 S.E.2d 136, 144 (S.C. Ct. App. 2003) (“It is apodictic that a plaintiff may only recover for injuries proximately caused by the defendant’s negligence.”). While there may have been some negligent conduct by Jessco, the proximate-cause determination means that Jessco could not have been held accountable to a third-party for that negligence. See, e.g., Howard v. Riddle, 221 S.E.2d 865, 866 (S.C. 1976) (“Plaintiff must show, as a matter of law, not only that defendant was negligent but also that his negligence was a contributing or proximate cause of the injury . . . .” (internal quotation marks omitted)).
Having established the arbitrator determined there was no actionable negligence on the part of Jessco, the court reasoned the re-grading allowance could only have been awarded as compensation for a breach of contract. Therefore, because the Policy unambiguously excluded coverage for breach of contract damages, the court found BMIC had no obligation to indemnify Jessco for the re-grading allowance paid to the Mazycks.

Having determined that BMIC owed a duty to defend Jessco in the underlying action, but did not owe a duty to indemnify Jessco for the re-grading allowance, the court vacated the district court’s judgment and remanded for further proceedings consistent with the opinion.
Part II of this blog post will discuss the decision of the district court on remand. We will post it on Tuesday.

Until then - have a wonderful Memorial Day. 